Which Arizona Owners Require the Bonds
Title 34 works through the word agent. A.R.S. §34-101 defines an agent as any county, city or town and its officers, boards or commissions, along with irrigation, power, electrical, drainage, flood protection and flood control districts, tax-levying public improvement districts and county or city improvement districts. Section 34-222 then requires anyone contracting to build, alter or repair a public building or public work for those bodies to furnish the bonds before the contract is executed, unless a statute specifically exempts the work. The bonds become binding on award.
Counties and the state reach the same bonds by different routes. A.R.S. §11-254.01 sends the erection of, repair of and alterations to county buildings to title 34, chapter 2, rather than the general county purchasing rules. State agencies buy construction under the procurement code, where §41-2574 requires 100 percent performance and payment bonds once a construction award exceeds the amount set by §41-2535, executed and furnished as title 34 requires and on its forms. ADOT contracts under §28-6923 also call for 10 percent bid security and title 34 bonds.
For a contractor, the working question is which article governs the bond. Chapter 2 covers design-bid-build public work. Chapter 6 covers construction-manager-at-risk, design-build and job-order-contracting services. Its bond and claim rules differ from chapter 2 in timing and notice mechanics.
For how Arizona's rules compare with federal, California and Texas requirements, see public works bond rules in all four states.
What the Statutory Bonds Say
Both bonds equal the full contract amount. The performance bond is solely for the protection of the public body and is conditioned on faithful performance under the plans, specifications and conditions of the contract. The payment bond is solely for claimants supplying labor or materials to the contractor or its subcontractors. Each bond must let the prevailing party in a suit recover reasonable attorney fees fixed by the judge, is payable to the public body and is filed with the contracting office.
The performance bond form in §34-222(G) runs through the original term, any extension, the life of any guaranty required under the contract and all authorized modifications, with notice of modifications to the surety waived. That language carries the warranty period into the bond, so a one-year or longer guaranty in the specifications stays on the contractor's surety program after acceptance. Subsection I deems every bond given under the article to be in the statutory form regardless of its actual wording.
Surety qualification is strict. Bonds must be executed solely by a surety holding a certificate of authority from the director of the Department of Insurance and Financial Institutions, and individual sureties are barred even if §7-101 would otherwise allow them. The bid invitation may not require a particular surety, agent or broker. If the prime contract requires subcontractor bonds, subsection H holds them to the same surety standard.
For how warranty obligations stay on a surety program after the job, see warranty and maintenance bonds after acceptance.
Bid Security on Design-Bid-Build and Alternative Delivery
Every notice inviting design-bid-build bids under §34-201 must require a certified check, cashier's check or surety bond for 10 percent of the bid, as a guarantee that the contractor will enter into the contract. The statutory bid bond form obligates the principal, if it fails to sign and give the bonds and certificates of insurance named in the standard specifications, to pay the difference between its bid and the larger amount the agent contracts for in good faith, up to the bond penalty. Security is returned to unsuccessful bidders, and to the winner when it executes a satisfactory bond and contract.
Design-build and job-order contracting procured by competitive sealed proposals follow §34-608. Design-build bid security is 10 percent of the agent's construction budget stated in the request for proposals, excluding design, preconstruction, finance and other related services. For job-order contracting, the agent sets the amount at no more than 10 percent of its estimate of the construction likely to be done in the first year. A proposal without required security is rejected unless the agent finds the defect nonsubstantial.
Insurance sits inside the bid bond condition. Because the surety's obligation turns on the contractor delivering the certificates of insurance the standard specifications require, a contractor that cannot place the specified insurance after award may face the same bid bond exposure as one that walks away. Pricing the insurance program before bid day is part of protecting the bid bond.
For bid bond underwriting and what happens after award, see how bid bonds work and what sureties check.
CMAR, Design-Build and JOC Bonds Under §34-610
For construction-manager-at-risk, design-build and job-order-contracting services, §34-610 requires performance and payment bonds only on and at the same time as a contract or amendment that commits the contractor to build for a fixed price, a guaranteed maximum price or another fixed amount within a set time frame. The bonds therefore follow the GMP amendment rather than the preconstruction agreement. For CMAR and design-build, each bond equals the price of construction and excludes design, preconstruction, finance, maintenance, operations and other related services.
Job-order contracts get flexible bonding. The agent may require a single bond for the full term, a separate bond for each year of a multiyear contract or a separate bond for each job order, initially sized on its reasonable estimate of the construction likely to be done. The payment bond protects those supplying labor or materials for the construction, not those providing design or other related services.
For a surety, an open-ended job-order contract with annual bonds looks different from a single GMP. Contractors should send the agent's bonding election and the estimated annual volume with the bond request so the surety can size the program to the work that is likely to be ordered.
For how public works contractors build their surety and insurance programs, see public works contractor insurance and bonding.
Making a Payment Bond Claim Under §34-223
A claimant that furnished labor or material and has not been paid in full 90 days after its last labor or material may sue on the payment bond for the unpaid balance. The statute adds notice steps only for a claimant that contracted with a subcontractor and has no contract, express or implied, with the prime. That claimant must first give the contractor a preliminary 20-day notice under §33-992.01 and a written 90-day notice within 90 days after its last labor or material, stating with substantial accuracy the amount claimed and the party it supplied or worked for.
The preliminary notice borrows from the mechanic's lien statute. It is due within 20 days after the claimant first furnishes labor or materials to the jobsite and must describe the work with an estimated total price, name the claimant and the party that hired it and identify the jobsite. A late preliminary notice reaches only work furnished within 20 days before it was given and afterward under §33-992.01(E). Under subsection F, it may be mailed first class with a certificate of mailing or by registered or certified mail.
Delivery of the 90-day notice differs by delivery method. Under §34-223 it may go by any means that provides written third-party verification of delivery to the contractor's office, place of business or residence. Under §34-611, which governs CMAR, design-build and JOC bonds, it must be served by registered or certified mail. Under both, suit is brought in the claimant's name no later than one year after its last labor or material.
For how Arizona's claim rules compare with federal, California and Texas rules, see payment bond claims on public work.
Bond Copies, Retention and Contract Terms That Touch the Bonds
An unpaid claimant, a party sued on the bond or the surety may apply in writing to the contracting body for a certified copy of the bond and contract, which is prima facie evidence of the original under §34-223(C). The applicant pays the reasonable fee the body sets for preparing the copies. Suppliers that do not know who wrote the bond can start there.
Retention under §34-221 runs beside the bonds. The owner retains 10 percent of each estimate until the contract is 50 percent complete, then on request releases half of the retained amount and holds no more than 5 percent of later payments while progress is satisfactory. The contractor may substitute qualifying securities for retained amounts. Sureties read retained balances as part of working capital, so retention timing on a large job can affect the contractor's capacity for the next bid.
Arizona also limits indemnity on public work. Under §34-226, a contracting agent may require the contractor to indemnify it only to the extent of the contractor's own negligence, recklessness or intentional wrongful conduct, and broader provisions are void. The statute still allows insurance requirements that comply with it, including additional insured status on general liability and designated insured status on auto liability, so the insurance exhibit and the indemnity clause should be read together with the bonds.
For the Arizona rules civil and utility contractors meet on public jobs, see Arizona civil and infrastructure contractor insurance.
Before You Ask for a Quote
What to Gather
- The agent's bid notice showing the 10 percent bid security and required bond forms
- The delivery method and, for CMAR or JOC, the GMP amendment or the agent's bonding election
- Standard specifications listing the insurance certificates the bid bond depends on
- Subcontractor and supplier list with first-delivery dates and preliminary notices received
- Warranty or guaranty terms the performance bond will carry after acceptance
- Current WIP schedule and retention balances by job
What to Ask the Insurer or Surety
- Does the surety hold an Arizona certificate of authority from the Department of Insurance and Financial Institutions?
- Will the surety bond each JOC year or each job order, and how will it size the first-year estimate?
- How long after acceptance will the surety treat the performance bond as open for the guaranty period?
- What does the surety want to see when a 90-day notice arrives from a sub-supplier?
- Does the surety want bonds from key subcontractors on this contract?
Quick Answer
Arizona public works for counties, cities, towns and covered districts need performance and payment bonds equal to the full contract amount before the contract is executed. Second-tier claimants give a preliminary 20-day notice and a 90-day notice to the contractor, and all claimants sue within one year of their last labor or material.
Common Mistake
Assuming a small Arizona public job needs no bonds because California and Texas use dollar triggers. Section 34-222 has none, so a contractor that bids without bonding capacity may face a bid bond claim if it cannot deliver the bonds.
Broker Perspective
A broker confirms which article governs the contract, whether the bonds attach at award or at a GMP amendment and how long the guaranty period keeps the performance bond open, then lines up the insurance certificates the bid bond depends on.
Coverage Impact
Bonds are credit: the contractor and its indemnitors repay any claim the surety pays. The insurance certificates required by the standard specifications are part of the bid bond condition, so gaps in the insurance program can create surety exposure as well as coverage questions.
The Same Requirement in Other States
Questions Buyers Ask
Does a late preliminary notice end an Arizona payment bond claim?
Not entirely. A.R.S. §34-223 incorporates §33-992.01(E), so a claimant that gives its preliminary 20-day notice late can still claim for labor or materials furnished within 20 days before the notice and afterward. Earlier deliveries are generally lost. The 90-day notice and the one-year suit deadline still apply in full, so counsel should check every date before a claim is filed.
When does a construction manager at risk in Arizona have to deliver the bonds?
Under A.R.S. §34-610, on and at the same time as a contract or amendment that commits it to build for a fixed price, a guaranteed maximum price or another fixed amount within a set time frame, which is usually the GMP amendment. Each bond then equals the price of construction, excluding design, preconstruction and other related services. Tell the surety when the GMP is expected so the bonds can be ready.
How do we serve the 90-day notice on an Arizona job-order contract?
By registered or certified mail, postage prepaid, addressed to the contractor at an office, place of business or residence, under A.R.S. §34-611. That differs from design-bid-build work under §34-223, which accepts any method with written third-party verification of delivery. Keep the mailing receipt, and file suit within one year after your last labor or material in either case.
Can a ready-mix supplier on an Arizona city job get a copy of the payment bond?
Yes. Under A.R.S. §34-223(C), a person that states it supplied labor or materials and has not been paid may apply in writing to the contracting body for a certified copy of the bond and the contract. The copy is prima facie evidence of the original, and the applicant pays the reasonable fee the body sets for preparing it.
Does our Arizona performance bond end when the town accepts the street?
Not necessarily. The statutory performance bond form in A.R.S. §34-222(G) runs through the life of any guaranty required under the contract, so a warranty period in the specifications keeps the obligation open after acceptance. Sureties typically keep that exposure on the contractor's program until the guaranty expires. Check the specifications for the warranty term and any separate maintenance bond requirement.
Official Sources
- A.R.S. §34-222 (performance and payment bonds; forms; surety), Arizona State Legislature. Full-amount performance and payment bonds before execution, binding on award, attorney fees, certificate of authority, no individual sureties, no required surety or agent, statutory forms including the guaranty period, subcontractor bonds and deemed statutory form. Verified 2026-10-24.
- A.R.S. §34-223 (payment bond claims), Arizona State Legislature. 90-day right to sue, preliminary 20-day and 90-day notices for claimants contracting with a subcontractor, third-party verified delivery, one-year suit limit and certified copies of the bond and contract. Verified 2026-10-24.
- A.R.S. §34-101 (definitions: agent), Arizona State Legislature. Agent includes counties, cities, towns and their officers, boards and commissions and listed districts; definitions of CMAR, design-build and design-bid-build. Verified 2026-10-24.
- A.R.S. §34-201 (bid security and bid bond form), Arizona State Legislature. 10 percent bid security by certified check, cashier's check or surety bond; certificate of authority; bid bond form tied to bonds and certificates of insurance; return of security. Verified 2026-10-24.
- A.R.S. §34-608, §34-610, §34-611 (alternative delivery bid security, bonds and claims), Arizona State Legislature. Design-build and JOC bid security; bonds at fixed price or GMP commitment; bond amounts equal to the price of construction; JOC bond options; 90-day notice by registered or certified mail under §34-611. Verified 2026-10-24.
- A.R.S. §33-992.01 (preliminary twenty-day notice), Arizona State Legislature. Notice due within 20 days after first furnishing, required contents, 20-day look-back for late notice and mailing methods. Verified 2026-10-24.
- A.R.S. §41-2574 (state procurement code performance and payment bonds), Arizona State Legislature. 100 percent performance and payment bonds on state construction awards above the §41-2535 amount, furnished as title 34 requires. Verified 2026-10-24.
- A.R.S. §28-6923 and §11-254.01 (ADOT and county construction), Arizona State Legislature. ADOT 10 percent bid security and title 34 performance and payment bonds; county building construction and repairs subject to title 34, chapter 2 (§11-254.01(E)). Verified 2026-10-24.
- A.R.S. §34-221 and §34-226 (retention and public works indemnity), Arizona State Legislature. Retention of 10 percent, half released at 50 percent completion with later retention capped at 5 percent and substitution of securities (§34-221); indemnity limited to the contractor's own fault with compliant insurance requirements allowed (§34-226). Verified 2026-10-24.
Reviewed by the Principal, Gleason Insurance Brokers, LLCUpdated