Owner Contract Forms and the Insurance Exhibit
On commercial work the owner's contract usually arrives with an insurance exhibit drafted by the owner's risk manager, lender or consultant. It may start from a standard industry form and then add owner-specific requirements: named additional insureds such as the lender, property manager and design team, specified endorsement editions, excess limits that must follow form and notice-of-cancellation duties the GC cannot always get from its carrier.
Read the exhibit for requirements that change price or availability, not only limits. Common pressure points include completed-operations additional insured status for a set number of years after completion, a dedicated per-project aggregate, a requirement that the GC's excess sit over the owner's own policies and an obligation to require identical terms from every subcontractor. Each item may need an endorsement, a carrier exception or a negotiated change.
The time to raise these points is during bid review, when the owner still expects comments. A short exception letter that names each requirement the GC's program cannot meet, and offers the closest available alternative, often settles the issue before it becomes a default notice after award.
- Named additional insureds beyond the owner, including lenders and managers
- Endorsement editions specified by form number
- Completed-operations duration after substantial completion
- Flow-down of identical terms to every subcontract tier
The endorsement basics behind these exhibits are explained on the main hub for general contractor insurance for projects.
OCIP and CCIP Participation on Commercial Jobs
Large commercial owners often sponsor an owner-controlled insurance program. As an enrolled GC, you typically submit a bid with insurance costs for enrolled work removed, provide payroll and subcontractor data for enrollment, follow the program's safety manual and report claims through the program administrator. Your own program stays in force for off-site operations, vehicles, tools and anything the OCIP excludes.
The details that hurt GCs are usually in the enrollment rules. Not every vendor is eligible: haulers, suppliers and some specialty trades may be excluded and must carry their own insurance under your subcontract. Coverage under the wrap may end on a schedule that differs from your contract exposure, and the annual GL policy usually needs a wrap exclusion that is drafted narrowly enough not to strip coverage from non-enrolled work.
Texas adds a statutory point. Insurance Code chapter 151 limits indemnity and additional insured requirements for a party's own negligence, but it carves out provisions in policies issued under consolidated insurance programs to the extent they list, add or delete named insureds. That interaction is worth confirming with counsel on any Texas wrap.
Owners and GCs sponsoring a program can review wrap-up programs placed by Gleason Insurance Brokers.
Enrollment, bid deductions and off-site coverage are explained in what an owner-controlled insurance program asks of enrolled contractors.
Tenant Improvement Versus Ground-Up Construction
Ground-up commercial work starts on open land or a cleared pad. The exposures are excavation, structural erection, crane work, weather and the builders risk values that grow as the shell goes up. Insurance and bonding are sized to the full project, and the owner usually controls builders risk or a wrap on larger jobs.
Tenant improvement work happens inside an existing building, often while other tenants stay open. The GC works on property it does not own and did not build, next to occupants who can be injured or disrupted. The questions shift to damage to the existing structure, property in the GC's care, custody or control, fire watch and hot work rules, after-hours access and whether the landlord's property policy or a builders risk policy responds to the existing building.
Ask whether the GL form limits coverage for damage to property the GC is working on, and whether the landlord's lease or work letter requires additional insured status for the landlord, the property manager and the tenant at the same time. TI contracts often come from the landlord and the tenant separately, with exhibits that do not agree with each other.
Office, retail, healthcare and hospitality exposures are broken out under commercial construction project risks.
Public Works Bonds and Prevailing Wage
Public owners require statutory bonds, and the trigger amounts vary by state. In California, Civil Code §9550 requires a direct contractor on a public works contract above $25,000 to give a payment bond before work begins, with an exception for certain state entity contracts. In Texas, Government Code §2253.021 requires a performance bond above $100,000 and a payment bond above $25,000, or above $50,000 when the governmental entity is a municipality. Arizona's A.R.S. §34-222 requires both bonds in the full contract amount on covered public building and improvement contracts.
These bonds are surety, not insurance. The performance bond protects the public owner and the payment bond protects those who supply labor and material. The GC signs an indemnity agreement with the surety. Each new public contract draws on bonding capacity, so a commercial GC moving into public work should share its pipeline with the surety before bidding a run of public jobs.
Public work also changes payroll. California Labor Code §1771 requires prevailing wages on public works above a small threshold, and higher wage rates can raise payroll-based premiums such as workers' compensation. Ask how the carrier will audit prevailing wage payroll and whether the job's payroll should be reported separately.
Who a payment bond protects and how claims work is explained under payment bonds on public and private work.
Design-Build and Delegated Design Exposure
Under design-build, the commercial GC holds the design contract with the owner and hires the architect and engineers itself. If the design is wrong, the owner's claim comes to the GC first. Many commercial GL forms limit or exclude claims arising from professional services, so a design error that causes a loss may fall outside the GC's liability program depending on the form and endorsements.
Several tools can address the gap. The design firms carry their own professional liability, though their limits may be modest and aggregate across all their projects. A GC may consider contractor's professional liability, which can respond to the GC's vicarious liability for design and, under some forms, to rework costs. Some owners require a project-specific professional policy covering the whole design team.
Delegated design creates a smaller version of the same exposure on conventional jobs: curtain wall, fire sprinkler, steel connections and other trade-designed systems. Check whether the subcontractor's professional coverage, not just its GL, meets the subcontract's design obligations. On bonded design-build work, ask the surety how the performance bond treats design obligations.
How sureties look at design risk in the bonded obligation is explained under performance bonds for design-build contracts.
How a Commercial Project Review Typically Works
On commercial work, the owner's contract form and any lender exhibit usually set the requirements, and tenant improvement, ground-up and design-build jobs can each change the answer. A review typically compares those requirements with the GC's program and the limits tower before the contract is signed.
These are common steps, not fixed rules. Insurers and sureties each apply their own guidelines and programs, the terms offered depend on the project and the individual risk, and coverage or bonds are subject to underwriting and to the conditions and exclusions of the forms that are issued.
- Documents: the prime contract form, the insurance exhibit, any lender exhibit and a wrap manual if the job is wrapped
- Scope: self-performed work, subcontracted share and any delegated design
- Limits: whether the exhibit calls for project excess above the annual tower
- Tenant improvement work: the lease or work letter, landlord requirements and the occupancy plan
- Surety: financial statements and work in progress for public or bonded private work
- Before signing: negotiated changes to exhibit terms the market may not offer
Project Excess and the Limits Tower
Commercial owners often require excess limits beyond what a GC carries on its annual umbrella, sometimes dedicated to a single project. Buying a project-specific excess layer keeps those limits from being shared with every other job and keeps a large loss on one site from eroding the GC's annual tower.
How the tower is built matters as much as the total. A follow-form excess policy generally tracks the terms of the primary policy beneath it, while a standalone or umbrella form can carry its own exclusions. Ask whether each layer follows the additional insured, primary and noncontributory and per-project aggregate terms the owner's exhibit requires, and whether completed-operations coverage continues for the same period at every layer.
Excess pricing depends on the project type, location, height, residential components, the subcontracting model and the GC's loss history. Giving the market clean contract, schedule and safety information tends to widen the options, especially on jobs with high-hazard components.
Primary and excess attachment on a single job is laid out under dedicated GL and excess limits for one commercial project.
Before You Ask for a Quote
What to Gather
- The owner's prime contract form and full insurance exhibit, including any lender exhibit
- OCIP or CCIP manual, enrollment forms and excluded-party list if the job is wrapped
- Project type, location, scope self-performed and subcontract share
- For TI work: the lease or work letter, landlord requirements and building occupancy plan
- For public work: the bid documents' bond and prevailing wage provisions
- Current excess and umbrella policies with each layer's form
What to Ask the Insurer or Surety
- Which exhibit requirements can our current program meet, and which need an exception letter?
- Does our wrap exclusion endorsement leave off-site and non-enrolled work covered?
- Does our GL form limit coverage for damage to an existing building we are working in?
- Does each excess layer follow form on additional insured and completed-operations terms?
- Could a design error on this design-build job fall outside our GL, and what professional coverage might respond?
- How much bonding capacity will this public contract use, and does the surety want to see the bid first?
Quick Answer
Commercial GCs work to owner-drafted insurance exhibits, wrap rules, statutory public works bonds and owner-required excess limits, so the review starts with the owner's documents rather than the GC's annual program.
Common Mistake
Deducting wrap costs from an OCIP bid without checking which vendors are excluded and whether the annual policy's wrap exclusion also removes coverage for off-site or non-enrolled work.
Broker Perspective
A broker compares the owner's exhibit, wrap manual, excess tower and bond requirements together, because a change to one usually changes the others.
Coverage Impact
Wrap exclusions, professional services exclusions and excess follow-form terms often decide whether a commercial loss reaches the GC's program, and public work adds statutory bond obligations that draw on surety capacity.
Requirements by State
Questions Buyers Ask
What insurance does a commercial GC still need on an OCIP job?
An OCIP usually provides liability, and sometimes workers' compensation, only for enrolled operations at the project site. The GC typically keeps its own auto, off-site liability, equipment, professional and any coverage the program excludes. Excluded vendors such as haulers or suppliers must carry their own insurance under the subcontract. Read the wrap manual's exclusions and termination terms against your contract before pricing the bid.
Why does tenant improvement work get underwritten differently than new construction?
In a TI, the GC works inside a building someone else owns, often with occupants nearby. Claims can involve damage to the existing structure, tenant business interruption and injuries to people who are not on the construction team. Some liability forms limit coverage for property in the contractor's care or the part of a building being worked on, so underwriters ask about occupancy, fire protection and hot work controls.
When are bonds required on Texas public work?
Texas Government Code §2253.021 requires a prime contractor on a public work contract to provide a performance bond when the contract exceeds $100,000 and a payment bond when it exceeds $25,000, or $50,000 for municipalities and certain joint boards. Both bonds run in the contract amount and must come from a corporate surety. Local bid documents may add their own requirements.
Does a contractor's GL policy respond to design errors on a design-build project?
Often not fully. Many GL forms limit or exclude claims arising from professional services, which can include design. The response depends on the form and endorsements, the design firm's own professional coverage and whether the GC carries contractor's professional liability. Review the design-build agreement's design warranty and the policy wording together before signing.
How much excess insurance should a commercial GC carry on one project?
No single amount fits every job. The owner's contract usually sets the minimum, and the right structure depends on project type, height, location, subcontracting model and the GC's existing umbrella. The more useful question is whether each excess layer follows the primary policy's additional insured and completed-operations terms and whether the limits are shared with other projects.
Official Sources
- Cal. Civ. Code §9550 (public works payment bonds), California Legislative Information. Payment bond required before work on public works contracts above $25,000, with a state entity exception Verified 2026-10-23.
- Cal. Labor Code §1771 (prevailing wages on public works), California Legislative Information. Prevailing wage requirement for workers on California public works above a small threshold Verified 2026-10-23.
- Tex. Gov't Code §2253.021 (public work performance and payment bonds), Texas Legislature. Texas performance bond threshold of $100,000 and payment bond thresholds of $25,000 or $50,000 for municipalities, bonds in the contract amount from a corporate surety Verified 2026-10-23.
- A.R.S. §34-222 (public works performance and payment bonds), Arizona State Legislature. Arizona public building and improvement contracts require performance and payment bonds in the full contract amount from a surety company Verified 2026-10-23.
- Tex. Ins. Code ch. 151 (consolidated insurance programs), Texas Legislature. Section 151.104(b) and 151.105 carve out consolidated insurance program policies from the additional insured limits Verified 2026-10-23.
Reviewed by the Principal, Gleason Insurance Brokers, LLCUpdated
My Contractors Insurance Quote is a website of Gleason Insurance Brokers, LLC. You can also find us on the Procore Construction Network.