Nevada final maps

Nevada Subdivision Improvement Bonds: Final Map Security, Reductions and Release

NRS 278.380 lets a Nevada governing body or planning commission require a subdivider to improve, or agree to improve, the streets and easements on a final map, and to secure that agreement with a good and sufficient bond or other security in an amount the local body sets. The amount, the accepted forms and the release steps come from local code: Clark County requires a 100 percent performance bond or cash deposit on its off-site improvement agreement, North Las Vegas sets surety at construction cost plus 10 percent and Washoe County takes a bond, letter of credit or deposit account on its subdivision improvement agreement. Release generally follows the agency's acceptance, with reductions allowed only on the terms each code states and a one-year warranty period after acceptance.

A contractor’s warranty bond for subdividers on a desk with subdivision drawings and a gold surety seal, a street of newly built houses behind it

Key Decision Points

  1. NRS 278.380 authorizes improvement security but leaves the amount to the governing body, planning commission or delegated director.
  2. Clark County allows one 80 percent reduction of a subdivision surety bond once only sidewalks, utility pads and boxes and slurry seal remain.
  3. North Las Vegas allows up to two reductions per off-site agreement and never below 10 percent of the original surety.
  4. Washoe County caps a reduction at 90 percent of completed work and 75 percent of the guarantee.
  5. Unset survey monuments need their own bond under NRS 278.371 if the map records before they are set.

What NRS Chapter 278 Requires, and What It Leaves to Local Code

The state statute is short. When a final map is approved, NRS 278.380 directs the governing body, planning commission or delegated director to accept or reject all offers of dedication, and it allows them, as a condition of accepting streets or easements, to require the subdivider to improve them or agree to improve them. If an improvement agreement is signed, subsection 3 allows the body to require that the agreement be secured by a good and sufficient bond or other security in an amount it determines. Any requirement imposed by a planning commission or director can be appealed under the local ordinance adopted under NRS 278.3195.

The statute names no percentage, no list of acceptable instruments and no release schedule. Those come from county and city codes and the agreement forms each public works department publishes, so a developer working in Clark County, North Las Vegas and Washoe County in the same year will post three different kinds of security on three different terms. The rest of this page walks through those three examples.

Monument Bonds and Final Map Deadlines

Nevada adds a separate, smaller security that developers sometimes miss. Under NRS 278.371, final survey monuments must be set before the final map records unless the subdivider furnishes a performance bond or other suitable assurance guaranteeing that a licensed professional land surveyor will set them on or before a day certain. The governing body or planning commission sets the amount, and under NRS 278.376 the county or city surveyor's certificate on the map states that a proper performance bond has been deposited if the monuments are not yet set.

Map deadlines shape when security is needed. NRS 278.360 gives a subdivider four years after tentative map approval to present a final map for the whole area or the first of a series, then requires each successive map in the series on or before the second anniversary of recording the first. Missing a deadline terminates the proceedings, and the governing body may grant an extension of up to two years after the successive-map period expires. A phased project therefore posts security map by map, and the surety sees a pipeline of bonds rather than one.

When parcels are merged and resubdivided without reverting to acreage, NRS 278.4925 requires the governing body to credit, on a pro rata basis, security already posted for improvements that will no longer be built, toward the same purposes on the new parcels. A developer redesigning a project mid-stream should ask for that credit in writing before posting new bonds.

Clark County: Off-Site Improvement Agreements and the 80 Percent Reduction

In unincorporated Clark County, Title 30 section 30.04.08C.3 requires the developer to agree, through posted security, to provide the required improvements before the subdivision map records or before a building or grading permit issues. The developer signs an off-site improvement agreement and delivers either a 100 percent performance bond or a cash deposit equal to the Director of Public Works' estimate of the total cost. A bond must be on the county's form from a surety licensed in Nevada that holds a Treasury Department Circular 570 certificate and an A.M. Best rating of A or better with a stable or positive outlook. Cash in lieu of a bond is limited to the federally insured amount, and the Public Works bonding checklist caps the cash-in-lieu agreement at $250,000.

Release turns on acceptance. Bonds are not released until the Director of Public Works accepts the improvements, unless the property reverts to acreage. Title 30 allows a one-time reduction of 80 percent of the surety bond on a subdivision project when only sidewalks, utility pads and boxes and slurry seal remain and the water and sewer utilities agree, with the remaining 20 percent released when the work is finished. The bonding checklist states that partial releases may be requested only on cash-in-lieu or cash bonds, so confirm with the Bonding Team how the reduction will be handled before planning cash flow around it.

The county's agreement form adds terms the surety will read closely. The agreement is recorded and runs with the land; the developer warrants the work for one year after acceptance; a drawn security must be replenished to its full amount within 30 days; and the county may draw on the security if work stops for 60 consecutive days. Title 30 measures the completion period at two years, from posting the bond in one subsection and from permit issuance in another, and an extension requires the bond to be recalculated and renewed. For residential subdivisions, the improvements must be accepted before final inspection of all homes in the subdivision.

North Las Vegas: Cost Plus 10 Percent and Two Reductions

North Las Vegas publishes its surety reduction and release procedure. Citing Municipal Code section 16.16.100, it sets improvement surety at 100 percent of construction costs plus 10 percent for contingencies, based on the city's bond and fee estimate, guaranteeing completion within 18 months or another period the city sets. The city also states that it raised the unit costs in private bond estimates to reflect public costs, so its estimate can run higher than the developer's engineer's number.

Reductions are limited and formula-driven. A developer may request no more than two reductions per off-site improvement agreement, in writing, while the agreement is not in default. No reduction is allowed while more than half the value of the work remains; once at least half is done, the surety may drop to the value of the remaining work plus 10 percent, but never below 10 percent of the original amount. The Director of Public Works acts within 30 days, and a refusal can be appealed to the City Manager within 30 days.

Release has its own path. After offsites are accepted, the one-year warranty begins only at final release of the surety, with a city review about 10 months into it. If offsites are accepted but some lots are not yet built, the surety can be released once the developer posts a damage bond of $2,500 per lot or records a restrictive covenant not to build. If a punch list sees no reasonable progress within 180 days, the city states it will begin collecting on the bond.

Washoe County: The Subdivision Improvement Agreement

Washoe County's standard subdivision improvement agreement, revised November 2023 and issued under Washoe County Code chapter 110, accepts a Faithful Performance Guarantee in the form of a bond, irrevocable letter of credit, certificate of deposit or savings or money market account, from a company or bank authorized to do business in Nevada. The subdivider sets a construction period not to exceed 12 months, and extensions of no more than one year require a replacement guarantee, which the county may increase if work has not proceeded diligently.

Reductions come at an extension or at each 12-month anniversary of the agreement. The maximum reduction equals 90 percent of the value of completed work but may not exceed 75 percent of the total guarantee, and a reduction is not acceptance of any part of the work. After acceptance, the subdivider warrants the improvements for one year. The form's recitals contemplate completing improvements before the final plat is filed, so confirm with the County Engineer whether a given map will record against security or after completion, since that decides when the bond is needed.

What a Surety Needs for a Nevada Improvement Bond

A subdivision bond is underwritten on the developer, not the site contractor. The surety will want the agency's approved bond estimate and agreement form, the phasing plan and final map schedule under NRS 278.360, the developer's and guarantors' financial statements, the construction loan terms and a schedule of every open improvement bond by agency, amount and expected acceptance date. For Clark County and North Las Vegas work, it also helps to show which reduction the developer expects to request and when.

Lot sales need the same attention. Clark County's agreement binds successors and third-party purchasers, and its performance bond form keeps the surety on the hook even if the developer no longer owns the property, while Washoe County's agreement keeps the subdivider liable regardless of later ownership. A purchase agreement with a homebuilder should therefore say who replaces the security, and by when, before the seller's surety is asked for a release.

Before You Ask for a Quote

What to Gather

  • The agency's approved bond estimate and its off-site or subdivision improvement agreement form
  • Tentative map approval date and the planned sequence of final maps
  • Survey monument status and any monument bond amount the agency sets
  • Developer and guarantor financial statements and the construction loan terms
  • Schedule of open improvement bonds by agency, amount and expected acceptance date
  • Draft lot or phase purchase agreements, including who replaces the security

What to Ask the Insurer or Surety

  • What instruments will the agency accept, and is cash in lieu capped?
  • What does the agency's estimate include beyond the engineer's cost, such as a contingency?
  • How many reductions are allowed, at what completion level and down to what floor?
  • Does the one-year warranty start at acceptance or at final release of the security?
  • What must be posted for lots that are still unbuilt when the offsites are accepted?
  • If we sell a phase, what replacement security will release our bond?
Quick Answer

NRS 278.380 lets Nevada cities and counties require a bond or other security for subdivision improvements in an amount they set, so local code governs: Clark County takes a 100 percent bond or cash deposit, North Las Vegas sets cost plus 10 percent and Washoe County accepts bonds, letters of credit or deposit accounts.

Common Mistake

Planning cash flow around a reduction the agency will not grant. North Las Vegas allows none while more than half the work remains, Washoe County caps reductions at 75 percent of the guarantee and Clark County limits its 80 percent reduction to specific remaining items.

Broker Perspective

A broker maps each agency's estimate, reduction rules and warranty start date against the final map schedule, so the developer knows how much surety capacity each phase will use and for how long.

Coverage Impact

Improvement bonds are surety credit, not insurance: they protect the city or county, and the developer and its guarantors repay any loss. Agreement forms such as Clark County's also require general liability naming the county as additional insured, and whether a policy meets that wording depends on its endorsements.

City Requirements in Nevada

The Same Requirement in Other States

Questions Buyers Ask

Does Nevada law set a percentage for subdivision improvement security?

No. NRS 278.380 allows the governing body, planning commission or delegated director to require a good and sufficient bond or other security in an amount it determines. The percentage comes from local code: Clark County uses a 100 percent bond or cash deposit based on its estimate, and North Las Vegas adds a 10 percent contingency to construction cost. Ask the agency for its approved bond estimate.

Can we record a Nevada final map before the survey monuments are set?

Yes, if the subdivider furnishes a performance bond or other suitable assurance that a licensed land surveyor will set them on or before a day certain, under NRS 278.371. The governing body or planning commission sets the amount, and the county or city surveyor's certificate on the map confirms the bond was deposited. It is separate from the improvement security for streets and utilities.

When can a Clark County subdivision bond be cut by 80 percent?

Title 30 allows a one-time reduction of 80 percent of the surety bond on a subdivision project when only sidewalks, utility pads and boxes and slurry seal remain on the streets and the water and sewer utilities agree. The remaining 20 percent stays until the work is finished and accepted. The county's bonding checklist limits partial releases to cash security, so confirm how the reduction will be processed.

What do we post in North Las Vegas when offsites are done but lots are still vacant?

The city's release procedure lets the original surety be released once the developer posts a damage bond of $2,500 per unbuilt lot or records a restrictive covenant not to build, which the city provides. The one-year warranty on the offsites then starts at the surety release. Confirm the current amount with the Construction Services Division before closing on any lot sale.

How much can Washoe County reduce our faithful performance guarantee?

Under the county's subdivision improvement agreement, a reduction may be allowed when an extension is granted or at each 12-month anniversary, up to 90 percent of the value of completed work but never more than 75 percent of the total guarantee. A reduction does not mean the county has accepted any of the work, and the one-year warranty starts only after acceptance.

Official Sources

  1. NRS 278.380 (final map approval; improvement agreements and security), Nevada Legislature. Acceptance or rejection of dedications; requirement to improve or agree to improve; agreement secured by a good and sufficient bond or other security in an amount the local body determines; appeal under the NRS 278.3195 ordinance. Verified 2026-10-25.
  2. NRS 278.360, 278.371, 278.376 and 278.4925 (map deadlines, monument bonds, surveyor certificate, credit of security), Nevada Legislature. Four-year and two-year final map deadlines and extensions; performance bond for unset monuments; surveyor certificate of the bond; pro rata credit of posted security after merger and resubdivision. Verified 2026-10-25.
  3. Clark County Code Title 30, Unified Development Code, sections 30.04.08C.3, 30.04.08C.7 and 30.06.11 (effective version posted October 2026), Clark County, Nevada. Security before map recording or permits; 100 percent bond or cash deposit; surety licensing, Circular 570 and A.M. Best requirements; cash limit; release on acceptance; one-time 80 percent subdivision reduction; cash installment releases with 10 percent retention; two-year completion and extension renewal; acceptance before final home inspections. Verified 2026-10-25.
  4. Clark County Public Works, Bond Processing: Posting Bonds checklist, Off-Site Improvements Agreement and Performance Bond examples, Clark County Department of Public Works. Bond options and $250,000 cash-in-lieu cap; partial releases limited to cash security; $1 million liability certificate naming the county; agreement recorded and running with the land; one-year warranty; 30-day replenishment; 60-day work stoppage; surety obligation continuing after a change in ownership. Verified 2026-10-25.
  5. City of North Las Vegas, Surety Reduction and Release Process, City of North Las Vegas Department of Public Works. Section 16.16.100 surety at construction cost plus 10 percent with 18-month completion; two reductions; 50 percent and 10 percent floors; 30-day decision and appeal; warranty from final release; $2,500 per lot damage bond or restrictive covenant; 180-day punch list rule. Verified 2026-10-25.
  6. Washoe County Subdivision Improvement Agreement (Washoe County Code 110), November 2023, Washoe County Community Services Department. Accepted guarantee forms; construction period up to 12 months and one-year extensions with replacement guarantee; reductions capped at 90 percent of completed work and 75 percent of the guarantee; one-year warranty after acceptance; liability regardless of ownership; recitals on completion before filing the plat. Verified 2026-10-25.

Reviewed by the Principal, Gleason Insurance Brokers, LLCUpdated

Bring the Contract and the Exhibits.

Share the project, the contract insurance exhibit and any bond or lender requirements. A licensed broker may review them as a courtesy when available, before anything is quoted. See how a project review works or who runs this site.

Full disclaimer about contract and insurance reviews

Contract and insurance reviews are a courtesy service that may be available at times, depending on our workload and on the size, timing and complexity of the project. A review is not guaranteed and is limited to insurance considerations. It is not legal advice and is not a substitute for advice from your own legal counsel, which you may need before signing a contract or obtaining coverage.

Next Level Experience

Insurance done right.