The 30-Day Plat Clock and Written Conditions
Chapter 212's approval procedure, as amended in 2019 and 2023, puts the city on a timetable. Under §212.009, the municipal authority must approve, approve with conditions or disapprove a plat within 30 days after filing, and a plat is approved unless it is disapproved within that period in line with §212.0091. The applicant may request written extensions of up to 30 days each. Section 212.0091 requires a written statement that clearly articulates each condition or reason, ties each one to the requirements of the subchapter, cites the statute or ordinance behind it and is not arbitrary.
For a developer, that changes the order of work. If fiscal security is a plat condition, the condition letter should name the ordinance section, and the bond should be ready to deliver when the response is filed. Section 212.0097 bars the city from requesting or requiring a waiver of these deadlines, and §212.0096 lets an applicant elect a faster alternative process if the city has adopted one. A broker who has the surety's approval in hand before filing keeps the bond from becoming the reason a plat response slips.
How plat security fits with payment bonds and lien reserves is covered in Texas developer insurance and bond requirements.
Water and Sewer Bonds in Subchapter K Counties
Some Texas counties carry a statute-defined bond. Section 212.0105 applies to an owner who divides a tract into residential lots of five acres or less in a county where a political subdivision is eligible for and has applied for state financial assistance under Water Code chapter 17, subchapter K. The plat must describe the water and sewer facilities and state when they will be fully operable, with an engineer's certification that they meet the model rules adopted under Water Code §16.343.
If the city requires a bond in that setting, §212.0106 controls its terms. The owner posts it before subdividing; it is payable to the presiding officer of the governing body, set at an amount the governing body finds adequate but not more than the estimated cost of the facilities, executed with approved sureties and, if a corporate surety is required, by a company authorized to act as a surety in Texas. It is conditioned on building the facilities to the model rules within the time stated on the plat or any extension. The owner may instead deposit cash, post a letter of credit from a federally insured institution naming the presiding officer as sole beneficiary or provide another acceptable financial guarantee.
The contractor building those lines carries its own exposures, covered under insurance and bonds for water and sewer contractors.
County Subdivision Bonds Outside City Limits
Unincorporated land follows chapter 232. Under §232.004, if the commissioners court requires a bond, the owner must post it before subdividing unless an alternative guarantee is provided. The bond is payable to the county judge, in an amount the court finds adequate to ensure proper construction of the roads, streets and drainage but not more than the estimated cost of that work, executed with sureties the court approves, and conditioned on construction to the court's specifications within a reasonable time the court sets. Section 232.0045 allows cash, a letter of credit from a federally insured institution naming the county judge as sole beneficiary or another acceptable guarantee instead.
Two county variations matter to developers working near the border or in larger counties. In counties covered by subchapter B, §232.027 requires a bond or cash deposit for water and sewer facilities not installed by the time of final plat approval, and a letter of credit qualifies only if it is irrevocable and issued by an FDIC-guaranteed institution. In urban counties under subchapter E, §232.105 lets the commissioners court contract with a developer for public improvements with county participation capped at 30 percent of the contract price, plus up to 100 percent of oversizing costs, and requires the developer to execute a corporate surety performance bond under Government Code chapter 2253.
The underwriting behind those bonds is explained under performance bonds for developers and contractors.
Limits on What a City or County Can Make the Developer Pay
Texas puts a ceiling on infrastructure exactions. Under §212.904, if a city conditions approval on the developer bearing part of the cost of municipal infrastructure through dedications, fees or construction costs, the developer's share may not exceed what is roughly proportionate to the proposed development, as approved by a licensed professional engineer retained by the city within 30 days of the developer's application. The developer may appeal to the governing body and then to county or district court, the city may not require a waiver of that appeal as a condition of approval, and a prevailing developer recovers costs and reasonable attorney's fees, including expert fees. Section 232.110 applies the same rule to counties.
The proportionality limit shapes the bond because it shapes the scope. Oversized lines or off-site roads beyond the development's proportionate share belong in a participation contract or a reimbursement agreement, not in the developer's bonded obligation. Section 212.906, added in 2023, also bars value-based review and inspection fees and limits when a city may require disclosure of the cost of public infrastructure improvements as a condition of approval or acceptance. How that disclosure limit interacts with a city's request for an engineer's estimate to size fiscal security is a question for counsel before the estimate is submitted.
Statewide Texas rules for contractors and owners are summarized on Texas construction insurance and bond rules.
Developer Participation Contracts Carry a Public Works Bond
When a city shares the cost of public improvements a developer builds, the bond changes character. Sections 212.071 through 212.073 let a city with 5,000 or more inhabitants contract with a developer, without competitive bidding, to build public improvements other than buildings related to the development, with city participation limits set in the statute. Section 212.073 requires the developer to execute a performance bond for construction of the improvements, by a corporate surety in accordance with Government Code chapter 2253.
Chapter 2253 is the Texas public work bond statute. Section 2253.021 describes a performance bond solely for the protection of the governmental entity, in the amount of the contract and conditioned on faithful performance according to the plans, specifications and contract documents, executed by a corporate surety under the Insurance Code. Whether a payment bond is also required on a participation contract, and in what amount, depends on how the contract and the city read chapter 2253, so the developer and its surety should settle that before the contract is signed.
Thresholds and claim rules under chapter 2253 are set out in Texas public works bond requirements under chapter 2253.
Reading a Texas City's Subdivision Bond Form
Because the statute leaves the terms to the city, the bond form is where the obligation is defined. Round Rock's published performance bond for subdivision improvements is a useful example. It recites that Section 4-98 of the city's Code of Ordinances requires a developer to file fiscal security conditioned on completing subdivision improvements within three years, binds the principal and a surety authorized in Texas to the City of Round Rock and includes a surety stipulation that changes, extensions of time and alterations do not affect its obligation, with notice waived.
The form also shows why a broker reads the condition line by line. Its recital measures the three years from permit issuance for the developer's Subdivision Improvement Construction Plan, while the operative condition measures them from acceptance of that plan. Which date governs changes when the surety's obligation could be called, so it is worth confirming with the city engineer before the bond is executed. Many Texas cities also require a separate maintenance bond at acceptance, and its term and percentage come from the local ordinance.
Local market conditions around Round Rock are covered under construction insurance in the Austin metro.
What a Texas Surety Wants Before Plat Filing
Texas subdivision bonds are underwritten on the developer, not the site contractor. A complete request typically includes the ordinance section and bond form the city or county will use, the engineer's estimate split between on-site, off-site and oversized work, any participation or reimbursement agreement, the developer's and guarantors' financial statements and a schedule of open plat and maintenance bonds. Sureties also ask who funds the improvements, whether a municipal utility district or other special district will reimburse costs and whether the site contractor is bonded to the developer.
Timing is the other variable. With a 30-day plat clock, the surety's approval, the indemnity agreement and the city's form should be settled before filing, not after a conditional approval letter arrives. Planning the release path at the same time, including any maintenance bond the city takes at acceptance, keeps capacity available for the next section of the development.
The full horizontal developer program, from acquisition to finished lots, is outlined in insurance and bonds for land developers.
Before You Ask for a Quote
What to Gather
- The city or county ordinance section requiring fiscal security, and its bond, letter of credit and maintenance bond forms
- Plat application, conditional approval letter and the cited statute or ordinance for each condition
- Engineer's estimate split by on-site, off-site and oversized work
- Any developer participation, reimbursement or special district agreement
- Developer and guarantor financial statements and the source of funds for the improvements
- Schedule of open plat, participation and maintenance bonds by obligee
- Site contractor's contract and any performance and payment bonds it provides to the developer
What to Ask the Insurer or Surety
- Does the city require security before recording, or may we build and record after acceptance?
- What percentage of the estimate and what forms will the city or county accept?
- Is any part of the scope beyond our roughly proportionate share under §212.904 or §232.110?
- Does §212.0106 or §232.027 apply to water and sewer facilities on this plat?
- If there is a participation contract, does the city require a payment bond as well as the §212.073 performance bond?
- When does the completion period in the bond form start, and what maintenance bond follows acceptance?
Quick Answer
Texas cities may require surety before approving development plans under Local Government Code §212.901, and counties may require road and drainage bonds payable to the county judge under §232.004; local ordinances set most amounts and forms within state limits.
Common Mistake
Bonding the full engineer's estimate without checking whether part of the scope exceeds the development's roughly proportionate share. Oversized work can belong in a participation or reimbursement agreement instead of the developer's own subdivision bond.
Broker Perspective
A broker reads the city's bond condition and completion date, confirms which statutes apply to water, sewer and county roads and has the surety's approval ready before the 30-day plat clock starts.
Coverage Impact
A subdivision bond is surety, not insurance: it protects the city or county, and the developer and its indemnitors repay any loss. Each open plat, participation and maintenance bond typically uses surety capacity until it is released.
City Requirements in Texas
- Georgetown Requirements
- Williamson County Requirements
- Celina Requirements
- Collin County Requirements
- Denton County Requirements
- Frisco Requirements
- Prosper Requirements
- Fort Bend County Requirements
- Harris County Requirements
- Katy Requirements
- Montgomery County Requirements
- Bexar County Requirements
- Comal County Requirements
The Same Requirement in Other States
Questions Buyers Ask
Can a Texas county make us post a bond before we subdivide outside city limits?
Yes, if the commissioners court requires one. Under Local Government Code §232.004, the bond is payable to the county judge, sized by the court to ensure proper construction of roads, streets and drainage and capped at the estimated cost of that work. Section 232.0045 lets you post cash, a letter of credit from a federally insured institution naming the county judge as sole beneficiary or another acceptable guarantee instead.
Can a Texas city ask us to waive the plat approval deadline while our bond is being issued?
No. Local Government Code §212.0097 bars the city from requesting or requiring an applicant to waive a deadline or approval procedure in the plat subchapter. You may request a written extension of up to 30 days under §212.009, and the city must approve it. Having the surety's approval ready before filing usually avoids the need for one.
Can a Texas city make us pay for an oversized water line through our subdivision bond?
Not beyond your proportionate share. Section 212.904 limits the developer's portion of municipal infrastructure costs to what is roughly proportionate to the development, as approved by an engineer the city retains, and gives you an appeal the city cannot make you waive. Oversizing is commonly handled through a participation or reimbursement agreement, which can carry its own bond.
What does a water and sewer bond under section 212.0106 have to say?
It must be payable to the presiding officer of the city's governing body, set at an amount the governing body finds adequate but not over the estimated cost of the facilities and conditioned on building them to the Water Code §16.343 model rules within the time stated on the plat or any extension. A corporate surety, if required, must be authorized to act as a surety in Texas.
Does a Texas subdivision bond end when the city accepts the streets?
Often the performance bond is released at acceptance, but many Texas cities then require a maintenance bond for a period set by ordinance. The statute does not set a statewide warranty term, so the city's subdivision ordinance and bond forms control. Ask for the acceptance letter and the maintenance bond requirement together so release and the new bond happen in the right order.
Official Sources
- Tex. Local Gov. Code ch. 212 (§212.009-.0097, §212.010, §212.0105-.0106, §212.071-.073, §212.901, §212.904, §212.906), Texas Legislature (Texas Constitution and Statutes). 30-day plat clock, written conditions and no-waiver rule; approval standards; water and sewer bond terms and alternatives; developer participation performance bond; municipal surety before plan approval; rough proportionality and appeal; value-based fee and cost disclosure limits Verified 2026-10-24.
- Tex. Local Gov. Code ch. 232 (§232.004, §232.0045, §232.027, §232.105, §232.110), Texas Legislature (Texas Constitution and Statutes). County road and drainage bond payable to the county judge and alternatives; subchapter B water and sewer bond and irrevocable letter of credit rule; urban county participation contracts with 30 percent cap and chapter 2253 bond; county rough proportionality Verified 2026-10-24.
- Tex. Gov. Code ch. 2253 (§2253.021, public work performance and payment bonds), Texas Legislature (Texas Constitution and Statutes). Performance bond solely for the governmental entity, in the contract amount, conditioned on faithful performance and executed by a corporate surety Verified 2026-10-24.
- City of Round Rock, Performance Bond for Subdivision Improvements (rev. Jan. 18, 2019), City of Round Rock, Texas. City Code Section 4-98 fiscal security, three-year completion condition, recital and condition start dates, surety waiver of notice of extensions Verified 2026-10-24.
Reviewed by the Principal, Gleason Insurance Brokers, LLCUpdated